Requirement of creating a project
comes from 2 main sources:
- Inside of company -> create R&D project, or Investment project…
- Outside of company -> create customer project - automatically from sales order (assembly processing), or manually and then link to sales order (optional)
Project can be created from
template, or manually.
Template:
There are 2 templates can be used
for project creation: standard WBS and standard Network.
Standard WBS – T-code CJ91
Create Project definition first:
Create standard WBS
structure:
Then save standard WBS
Standard Network – T-code CN01
First enter information for Std
Network header:
Then
create activities under this Network
Enter Work center, Working hours,
activity type…. Then save the Std Network.
Enter the std WBS element to the
activity in case we want to create this activity under one WBS element.
Create project from template
T-code: CJ20N
Enter standard project:
è New
project is generated as the templates: